Work on 10th Avenue unlikely to be completed within stipulated time

The construction work of 10th Avenue continues at a snail’s pace and it is unlikely that it will be completed in the given deadline of 18 months.

Sources told Dawn that the pace of work shows that this project will take several years to complete as 12 out of 18 months have already passed and so far, the progress on work is less than 15pc.

Work on the project kicked off in March last year and as per the PC-1, the project was slated to be completed in 18 months at a cost of Rs10.2 billion.

This project is funded by the federal government, being executed by Capital Development Authority (CDA).