Samanabad underpass to open on 31st

The Samanabad-Gulshan Ravi underpass will be ready for motorists from July 31.

Though the construction work faced a bit of delay due to rains, shifting of major sewer lines, and other services, officials claim that the project is being completed two months before its actual deadline of Sept 30, as mentioned in the contract.

“The construction work on the project had been launched in December last year,” Commissioner Muhammad Ali Randhawa told Dawn on Friday.

“And under the contract, the completion deadline is Sept 30. But since the government wants its completion as early as possible, we are trying our best to do so.”