Rs1.5bn allocated to fast-track Warsak Canal Remodelling Project

PESHAWAR: The provincial government has significantly enhanced funding for the Remodelling of Warsak Canal System, increasing the allocation from Rs 650 million to Rs 1,500 million to ensure the timely completion of the vital water and irrigation project for Peshawar and Nowshera.

Through the efforts of Adviser to the Khyber Pakhtunkhwa Governor on Industries, Commerce, Technical Education, Irrigation, and Public Health Engineering, Dr Muhammad Irshad, the Planning and Development Department KP approved the additional funds.

Dr Irshad visited the project site alongside the Secretary of Irrigation and other senior officials, where the Project Director gave a comprehensive briefing on the physical and financial progress of the scheme.

Speaking during the visit, Dr Irshad termed the Warsak Canal Remodelling System a “lifeline” for Peshawar and Nowshera, noting that its completion would fulfill nearly 80 percent of Peshawar’s drinking water requirements.

He stated that out of the 5.5-kilometre project stretch, four kilometres had already been completed, while excavation work on the remaining section was progressing rapidly.

“The timely completion of public welfare projects like the Warsak Canal System is essential to boost agriculture, ensure sustainable drinking water supply, and generate economic opportunities,” the adviser remarked, adding that the remaining 1,120-metre tunnel excavation is expected to be completed by June 30, 2027.

According to the project briefing, the initiative includes the construction of a 5.2-kilometre auxiliary irrigation tunnel from Warsak Dam with a capacity of 700 cusecs.

The capacity of the Warsak Gravity Canal is being enhanced from 285 to 456 cusecs, while the Lift Canal’s capacity is being upgraded from 200 to 290 cusecs. To lift an additional 90 cusecs of water, the existing pump house is being upgraded alongside the construction of Pump House-II.

Furthermore, a 66kV grid station is being upgraded to 132kV with dedicated high-tension transmission lines to ensure uninterrupted power supply to the pumping infrastructure.